J321 Zawtika Development Project Phase 1C Construction Project was Completed

On February 10, 2018, with the final load-out of WP10 and smooth departure from the port, CSE accomplished all the construction work stipulated in the contract.

The 40,000-ton jackets and piles fabrication project (WP8/WP9/WP10/WP11) began on November 8, 2016, and ended on February 10, 2018, with a fabrication duration of 15 months. No-loss working hours of 2.8 million and zero non-conformity delivery were recorded. Standard and efficient loading and unloading operations were carried out for a total of six shipments.

The project pays great attention to early and effective quality risk identification, sets standards, specifications and procedures for quality control at all levels in accordance with the requirements of the owner's specifications. In addition, we work with the construction-related teams to strengthen the quality process control and ensure that the project is delivered with high quality.